top of page

Our Work

Dedicated to achieving the highest standards

Excavate & Reinstate specialises in constructing and altering substation plinths throughout the United Kingdom. Our multi-utility teams are adept at handling a wide range of projects, from building new plinths to modifying existing ones.

​

When tasked with substation plinth works, our typical process includes:

​

  1. Site assessment and preparation

  2. Excavation of the designated area

  3. Installation of the plinth foundation

  4. Placement of grating and necessary electrical conduits

  5. Concrete pouring and finishing of the plinth

  6. Application of tarmac or other specified surfacing

  7. Landscaping and soil reinstatement around the plinth

 

Our comprehensive service ensures that the finished plinth is ready for the installation of new electrical substations or the upgrade of existing ones. We work meticulously to meet the exact specifications required for each unique project.

​

Excavate & Reinstate's expertise extends to various groundwork and excavation tasks associated with utility infrastructure. Whether you need a new substation plinth constructed or an existing one altered, our skilled teams are equipped to deliver high-quality results across the UK.

​

For professional groundwork solutions tailored to your substation needs, contact Excavate & Reinstate. We're committed to laying solid foundations for your utility projects throughout the United Kingdom.

​

A brick-built substation plinth under construction

01

Excavate and Reinstate Ltd constructed a durable substation plinth in Liverpool, completed to a high standard. The process began with precise excavation and compaction of the sub-base, followed by concrete blinding and shuttering installation. A reinforced concrete base was poured, brickwork and ducting were added, and the area was backfilled with compacted Type 1 MOT. Earthing and steelwork, including earthing clamps, were securely installed. The project was finished with the top base plinth concrete pour, creating a strong, level foundation ready for substation installation.

02

Excavate & Reinstate Ltd has successfully completed the full excavation and construction of a substation plinth in Birmingham, delivering a high-quality finish in line with the client’s design specifications. The works began with a careful and controlled excavation, ensuring all underground services were identified and protected. A clean and stable base was established with the installation of concrete blinding, followed by the secure placement of shuttering to prepare for the base concrete pour.

Once set, the base plinth concrete was poured and levelled with precision, providing a strong and durable foundation. Blockwork was then constructed to the exact requirements of the client’s design, with each course laid accurately to ensure structural integrity and alignment. Type 1 MOT was subsequently installed and compacted in 200mm layers, methodically brought up to the block level to guarantee long-term stability.

To complete the works, top plinth shuttering and steel reinforcement were installed in full accordance with the substation design. All stages were carried out to a high standard of workmanship, with a strong emphasis on safety, compliance, and attention to detail throughout the project.

A substation plinth under construction

03

WhatsApp Image 2024-08-30 at 13.35_edite

Excavate & Reinstate Ltd is progressing well with the substation plinth project in Yorkshire, having successfully delivered all key groundwork and structural phases to date. The area was first excavated, levelled, and compacted using a whacker plate, creating a solid base for construction. Concrete blinding was then laid, and markers set out to define the precise siting of the plinth.

Shuttering was constructed to the required dimensions, including a letterbox opening for service routes. Steel reinforcement was installed and the shuttering securely braced, ready for the concrete pour. The concrete was placed and finished to a high standard, then allowed to cure under controlled conditions.

With the concrete now fully cured, the shuttering has been removed, exposing a clean, well-formed plinth. Ground preparation is currently underway around the structure, readying the site for the next phase of substation installation. The project continues to move forward with precision and attention to detail at every stage.

04

Excavate & Reinstate Ltd has successfully delivered the construction of a substation plinth as part of a large-scale project in Devon. The works began with a carefully executed excavation to the required depth and footprint, with all underground services identified and protected. A clean, level layer of concrete blinding was then laid to provide a stable working base.

A large shuttering structure was erected to suit the design, including provisions for duct entries and a letterbox opening. Ducting pipework and steel reinforcement were installed with precision, ensuring full compliance with structural and service requirements. The concrete pour followed, with the mix carefully placed and compacted to form a strong, smooth finish. After curing under controlled conditions, the shuttering and temporary earth supports were removed.

With the structure fully exposed, earthing cables were installed on a prepared bed of sand, ensuring proper protection and alignment. The completed concrete plinth, with its accurately formed letterbox opening, now stands ready to receive the substation and its associated components, built to exacting standards throughout.

WhatsApp Image 2024-09-25 at 07.58_edite
bottom of page